|
In 1871, German
immigrant Rudolf Haffenreffer opened a brewery in Boston’s Jamaica
Plain neighborhood. At peak production, the brewery employed many of
the surrounding residents and produced over half a million barrels
of beer a year. When it closed in 1965, the facility, which had
grown to include many interconnected buildings, was abandoned and
fell into disrepair. In 1983 The Jamaica Plain Neighborhood
Development Corporation purchased the dilapidated complex and set
out to revitalize the buildings, bringing new vitality to the
surrounding community.
The landmark
brewery was once a bustling hub frequented by patrons who ranged
from laborers to Red Sox legends. In 2005 the final phase of
restoration, including the creation of commercial, industrial and
office spaces within the complex, was taken on by Commodore
Builders. Working closely with architect Stephen Baker of Baker/Wohl.
Architects and Project Manager Jennifer Pinck of Pinck & Co., the
challenge was to honor the past while revitalizing the buildings,
bringing them up to today’s building codes and providing a new
circulation plan to integrate the complex.
The buildings
were constructed between 1879 and 1920. Over the years, new segments
were added as needed. More than 8 decades later, those additions
posed significant construction challenges. In addition to historical
preservation considerations, there were drastically uneven floors,
unusually shaped buildings, 4-foot drops between building floor
alignment and cavernous rooms. Four-foot thick concrete foundation
walls and masonry fire-walls, along with thousands of square feet of
highly flammable cork insulation adhered to ceilings and exterior
walls, added up to a complicated structure. “It was a challenge,”
according to Jennifer Pinck, who managed the construction process
for JPNDC. “We had to put a lot of work into the project before we
could begin to build.”
Restoration
took place in the 8 interconnected buildings in the Main Block and
in Building K, leaving building D for a future phase. Some of the
common corridors provided access to existing tenants, adding the
challenge of maintaining safe occupancy while virtually gutting
adjacent space. Significant planning was required to maintain the
infrastructure to keep this occupancy and minimize disruption to
their operations. Boston Pretzel was producing product for Super
Bowl Sunday. When a new steel structure and cast-in-place concrete
mezzanine floor were installed directly over their kitchen and food
prep facility, the Commodore team built a cocoon-like structure to
ensure that football fans were not deprived of their favorite
snack.
Building
circulation and handicapped access were important elements of
building improvements. Floors were leveled and ramps were
constructed to navigate the 4-foot drops between buildings. A
chairlift and elevator were installed to connect the buildings.
Passageways were cut through 4-foot thick brick and concrete walls.
Because of the Brewery’s historical value, aspects of the renovation
required further approval by the National Park Service. Windows
were measured exactly to meet the restoration requirements and were
custom fit to the existing openings. A hung ornamental stair was
saved and restored, suspended in place during construction. With the
addition of a final flight of concrete steps with a railing system
comprised of stainless steel panels, it now provides access to the
penthouse.
Masonry walls
were water blasted to remove layers of unstable paint without
disrupting the easily scarred brick and mortar. National Park
guidelines required original historic fabric to be maintained as
much as possible, leaving exposed brick and limiting painted areas.
Cork insulation adhered to the ceilings in a number of the buildings
posed a significant fire hazard and was completely removed. The
cork removal exposed a rotted ceiling, impacting the schedule and
coordination of the installation of the new roof. In building E, a
4-story tall timber grain hopper, a vestige of the building’s beer
producing days, measured 20 feet by 35 feet. It was cut into
sections and carted away.
An entire new
utility infrastructure was installed throughout the complex. A new
HVAC system, power system, fire alarm and sprinkler were put into
place. The electrical distribution system in the Main Block was
revised with two main electrical distribution services.
With the
renovation came a new entryway and freshly paved parking area. The
character and industrial sense of the building were preserved by
deliberately maintaining a rough looking interior. Concrete acid
stained floors extend throughout the complex, with high open
ceilings, industrial style pendant lights and strip lighting.
Ornamental parts of the old brewery, including old doors, handles
and unique structures punctuate the walls. Vaulted ceilings and a
series of arches maintain the rustic look.
Working closely
with the JPNDC team of Jennifer Faigel, Andy Waxman and Lisa King,
the abandoned brewery has been restored to a bustling hub. It is
home to many local businesses and once again an asset to the
surrounding community. |
|
 |